No upcoming meetings 2020-04-07

Alena Staffer#350 - Project structure definition

Status:
Done
Assignee:
Alena Staffer
Estimated time:
1.00 h (Total: 12.00 h)
Task type:
Analysis & Consulting
Priority:
Normal
Due date:
2017-11-22
Start date:
2017-11-22
Spent time:
1.00 h (Total: 2.00 h)
Created:
2017-11-13 16:15
Closed:
2017-02-14 16:18
Milestone:

Skill 1 required?:
no

Sprint:
Story points:
0
MoreLess

Define tree structure of projects which will be tracked within the system. 

Example 1:

Realization Projects

> customer 1

> customer 2

> customer 3

Support Projects

> customer 1

> customer 2

> customer 3

Office

CRM

Administration

Example 2:

Product 1

> customer 1

> customer 2

> customer 3

Product 2

> customer 1

> customer 2

.....

Sub tasks

Analysis & Consulting #351: Project templatesDonePeter Project Man

Display previewUpdate
Setting & Support #359: Projects Structure + TemplatesDoneRobert Kovacik

Display previewUpdate

Related tasks:

 
precedes Implementation of IS - Analysis & Consulting #349: User roles and personal pages Done Alena Staffer 2017-11-24 2017-12-03

Budget

Plan/Reality: € 0.00 / -€ 40.00
Plan Reality
Incomes: € 0.00 € 0.00
Total costs: € 0.00 € 40.00
Personnel costs:
€ 0.00
Spent time: 2.0 hrs. / € 40.00
Expenses:

€ 0.00

€ 0.00

Profit:

€ 0.00

-€ 40.00
Profit margin 0.0 %
Net margin 0.0 %