No upcoming meetings 2020-04-10

#40 - Evaluation of draft documentation

Status:
New
Estimated time:
40.00 h
Task type:
Task
Priority:
High
Due date:
2018-03-11
Start date:
2018-03-10
Spent time:
Created:
2017-11-12 11:58

Material:
Skill 1 required?:
no

Sprint:
Story points:
0
MoreLess

Go thrue enclosed documents, write review, next week will be meeting

Related tasks:

 
following (5 days) Client Project - Task #39: Review meeting Realisation Manager Française 2018-01-23 2018-03-04
Copied from Client Project - Task #37: Documentation for Block no 1 New Robert Kovacik 2017-12-15 2017-12-22

Budget

Plan/Reality: € 0.00 / -€ 120.00
Plan Reality
Incomes: € 0.00 € 0.00
Total costs: € 0.00 € 120.00
Personnel costs:
€ 0.00
Spent time: 6.0 hrs. / € 120.00
Expenses:

€ 0.00

€ 0.00

Profit:

€ 0.00

-€ 120.00
Profit margin 0.0 %
Net margin 0.0 %